Approve a Development Impact Fee Credit Agreement related to Parcel Map No. 20508 and Design Review No. 22-007
End
RECOMMENDATION:
Recommendation
Approve and authorize the City Manager to execute a Development Impact Fee Credit Agreement with CPL Slover LLC, a Delaware limited liability company, related to Parcel Map No. 20508 and Design Review No. 22-007, located north of Slover Avenue at Banana Avenue, for the required construction of offsite improvements at the intersection of Slover Avenue and Calabash Avenue.
End
COUNCIL GOALS:
• To invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the City's existing infrastructure.
• To invest in the City’s infrastructure (streets, sewers, parks, etc.) by providing for the development of new infrastructure.
DISCUSSION:
On June 21, 2022, the Planning Commission approved Tentative Parcel Map No. 20508 (TPM No. 22-002) and Design Review No. 22-007 for the construction of a 289,875 square foot warehouse building, located north of Slover Avenue at Banana Avenue. The building square footage changed slightly and was permitted as a 291,742 square foot warehouse building.
Chapter 21, Article VI - Construction and/or Dedication In-Lieu of Development Impact Fees (Section 21-151 through 21-154) of the Fontana Municipal Code establishes a policy allowing in-lieu fee credit agreements between the City and developers. This provides an alternative method for satisfying a developer’s obligation to mitigate impacts from the development other than through payment of development impact fees.
This Development Impact Fee Credit Agreement for Circulation Fees will provide fee credits toward the applicant’s development impact fee obligations for the construction of infrastructure (circulation) at the intersection of Slover Avenue and Calabash Avenue as shown on Exhibit B and as follows:
Subject Development Construction In-Lieu Net Development
Fee Obligation Amount Fee Obligation
Circulation $1,193,224.78 $1,221,421.98 $0.00
Total $1,193,224.78 $1,221,421.98 $0.00
FISCAL IMPACT:
The approval of the Development Impact Fee Credit Agreement results in a reduction of the developer’s Circulation fee for the project.
MOTION:
Approve staff recommendation.