Title: Fontana Lewis Library & Technology Center Entry Precast Stair Replacement
Attachments: 1. BidResultList -PW-24-227-SB.xlsx, 2. Project Report - PW-24-227-SB.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

FROM:

Public Works

 

SUBJECT:

Title

Fontana Lewis Library & Technology Center Entry Precast Stair Replacement

End

 

RECOMMENDATION:

Recommendation

Award Bid and Authorize the City Manager to execute a contract with Ace Capital Engineering of Lake Forest, CA in the amount of $123,158.20 to Replace Precast Stairs of Lewis Library Entry and authorize a 10% contingency in the amount of $12,315.82

End

 

COUNCIL GOALS:

•                     Invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.

 

DISCUSSION:

The Lewis Library & Technology Center entry stairs is in desperate need of new precast entry stairs.  The stairs are showing signs of cracks, chips, and damage in multiple areas of the stair entry.  The bidding process for the Fontana Lewis Library & Technology Center Entry Precast Stair Replacement bid (PW-24-227-SB) was conducted by City staff in May and June 2024.  Five hundred twenty-seven (527) vendors were notified of the bid. Bid packets were downloaded/received by twenty-four (24) vendors and we received four (4) bid responses. Thirty-one (31) Fontana vendors were notified. One (1) Fontana vendor response was received.  The bid closed on Thursday, May 23, 2024, and the City received a total of four (4) bids.

 

After reviewing each individual company that provided a bid for the project, the Purchasing Office has recommended the contract be awarded to Ace Capital Engineering of Lake Forest, CA.  Ace Capital Engineering submitted all the necessary documents and therefore is the most responsible and responsive bidder.

 

FISCAL IMPACT:

The total fiscal impact associated with the approval of this item is $135,474.02 including contingencies.  Sufficient funds are budgeted in the current FY 2024/2025 budget, in the Lewis Library Steps Project No. 37300004-103-A-8329.

 

MOTION:

Approve staff recommendation.