Title: Reimbursement Agreement Between the City of Fontana and IE Centerfield, LLC (IE) for the Sierra Avenue Basin Storm Drain Improvement Plans
Attachments: 1. 2024.09.10 File 21-3269 Reimbursement agreement between the City of Fontana and IE Center Field LLC (Fontana Courtplace)-c1.docx
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

FROM:

Engineering

 

SUBJECT:

Title

Reimbursement Agreement Between the City of Fontana and IE Centerfield, LLC (IE) for the Sierra Avenue Basin Storm Drain Improvement Plans

End

 

RECOMMENDATION:

Recommendation

Approve Reimbursement Agreement between the City and IE Centerfield, LLC for the Sierra Avenue Basin Storm Drain Improvement Plans for the City to utilize in the installation of a Basin Storm Drain on Sierra Avenue, Juniper Avenue, and Jurupa Avenue.

End

 

COUNCIL GOALS:

•                     To invest in the City’s infrastructure (streets, sewers, parks, etc.) by providing for the development of new infrastructure.

•                     To invest in the City’s infrastructure (streets, sewers, parks, etc.) by utilizing Measure-I Funds wisely.

 

DISCUSSION:

The City holds fee title ownership to 4.72 acres of storm drain basin parcels, identified by Assessor Parcel Numbers 0255-101-22-0000 and 0255-101-23-0000. These parcels are located on Sierra Avenue, situated between Santa Ana Avenue to the north and Jurupa Avenue to the south, within the City of Fontana.

 

As part of the City's Capital Improvement Project (CIP), there was a recognized need to enhance the functionality of Sierra Avenue and Juniper Avenue through the construction of a master plan storm drain. IE Centerfield, LLC was commissioned to design the storm drain construction plans for this CIP. Following a thorough review by the City, the plans were approved and subsequently utilized for the construction process.

 

FISCAL IMPACT:

The fiscal impact associated with the approval of this item is $231,758.10 and is included in the 2024-25 capital budget in the Courtplace project # 37600063 in Fund 622 - Storm Drain Fund.

 

MOTION:

Approve staff recommendation.