File #: 25-0630    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 10/16/2025 In control: City Council Meeting
On agenda: 12/9/2025 Final action:
Title: Final Acceptance of the Sidewalk Reconstruction Project #1 (Grids 29, 35, 36, and 42) (DE-24-108-SB)
Attachments: 1. Attachment No. 1- Sidewalk Project #1.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

FROM:

Engineering

 

SUBJECT:

Title

Final Acceptance of the Sidewalk Reconstruction Project #1 (Grids 29, 35, 36, and 42) (DE-24-108-SB)

End

 

RECOMMENDATION:

Recommendation

Accept as complete the work performed by SNZ Contractors, Inc. for the Sidewalk Reconstruction Project #1 (Grids 29, 35, 36, and 42) (DE-24-108-SB).

End

 

COUNCIL GOALS:

                     To invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.

                     To invest in the City’s infrastructure (streets, sewers, parks, etc.) by providing for the development of new infrastructure.

                     To invest in the City’s infrastructure (streets, sewers, parks, etc.) by focusing on relief of traffic congestion.

 

DISCUSSION:

On February 27, 2024, the City Council authorized the award of a construction contract to SNZ Contractors, Inc. in the amount of $232,155.00 and authorized a contingency amount of $23,215.50 for a total contract authorization of $255,370.50 for the Sidewalk Reconstruction Project #1 (Grids 29, 35, 36, and 42).

 

Construction began in July 2024 and was completed in December 2024.  The project was successfully completed for the final amount of $233,788.00, an increase of less than 1% from the original contract amount of $232,155.00 and $21,582.50 under the total authorized budget.  The proposed improvements for Sidewalk Reconstruction Project #1 consisted of the rehabilitation of existing sidewalk, eliminating severely damaged conditions.  The project improved sidewalk walkability, increased sidewalk service life, and enhanced the safety of pedestrian traffic.

 

A stop payment notice was filed by a subcontractor during construction, which temporarily delayed project acceptance.  This issue has since been resolved, allowing the project to proceed to final acceptance.

 

FISCAL IMPACT:

As part of the action to accept the construction of the Sidewalk Reconstruction Project #1 (Grids 29, 35, 36, and 42) (Bid No. DE-24-108-SB) as complete for a total of $233,788.00, the City will take over the maintenance of this public infrastructure.  Appropriate funding for the maintenance work is included in the FY 2025-26 Budget under the Public Works Department, Utilities and Streets Division.

 

MOTION:

Approve staff recommendation.