FROM:
Public Works
SUBJECT:
Title
Final Acceptance of the Village of Heritage Pool Deck Repair Project (MS-106-PW-22).
End
RECOMMENDATION:
Recommendation
1. Accept as complete the work performed by Masterseal Corporation for the Village of Heritage Pool Deck Repair project and approve the final construction cost of $223,200.
2. Authorize the City Engineer/Director of Public Works to file a notice of completion and release the 5% retention.
End
COUNCIL GOALS:
• Invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.
DISCUSSION:
On April 12, 2022, the City Council awarded a contract to Masterseal Corporation in the amount of $219,500 and authorized a 10% contingency fund of $21,950 for the performance of pool deck repair work at the Village of Heritage Pool Deck Repair Project (MS-106-PW-22).
The project was completed on August 5, 2022 at a final construction cost of $223,200. One (1) contract change order was executed in the amount of $3,700 during the performance of this contract. All work has been completed to the satisfaction of the City.
This project replaced the existing worn and damaged pool deck coating with a new deck coating that includes a 5-year warranty on labor and materials and has a projected 10-year life expectancy.
FISCAL IMPACT:
The funding for this project was budgeted out of LMD 2 Fund 396 in ORG # 39638205. Remaining funds for this project will be returned to fund balance.
MOTION:
Approve Staff Recommendation