Legislation Details

File #: 26-1268    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 9/10/2026 In control: City Council Meeting
On agenda: 11/10/2026 Final action:
Title: Award a Contract for the Public Works East Yard Fencing Project (PW-27-07-SB)
Attachments: 1. Attachment No. 1- Summary Bid Results - PW-27-07-SB.docx, 2. Attachment No. 2- Summary Bid Results - PW-27-07-SB.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

FROM:

Public Works

 

SUBJECT:

Title

Award a Contract for the Public Works East Yard Fencing Project (PW-27-07-SB)

End

 

RECOMMENDATION:

Recommendation

Award and Authorize the City Manager to enter into a contract with D’Ybanag Construction, Inc. of Perris, CA in the amount of $385,277.77 and authorize a 10% contingency in the amount of $38,527.77 for the installation of a block wall and wrought iron fence around the new Public Works & Engineering East Yard Project (PW-27-07-SB)

End

End

 

COUNCIL GOALS:

•                     Practice sound fiscal management by living within our means while investing in the future.

•                     Invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.

 

DISCUSSION:

The Public Works & Engineering Department requires the installation of a perimeter block wall and wrought iron fence around the new Public Works East Yard facility, located at 16641 Orange Way, to enhance the security of the facility.

 

The Purchasing Division formally advertised the project under Bid No. PW-27-07-SB, and bids were opened electronically at 2:00 P.M. on August 13, 2026. Purchasing notified nine hundred fifty-eight (958) vendors. Bid packets were downloaded/received by one hundred forty-two (142) vendors, and twenty (20) bid responses were received. Five (5) Fontana vendors were notified. No Fontana vendor responses were received.

 

A thorough evaluation of all twenty responses was conducted by the Purchasing Division. Based on this evaluation, D’Ybanag Construction Inc., located in Perris, CA, was determined to be the lowest, most responsive, and responsible bidder meeting all structural and administrative specifications.

 

FISCAL IMPACT:

The fiscal impact associated with the approval of this item is $385,277.77 plus a contingency of $38,527.77 and are included in the FY2026-27 budget in project 37300011-632-A-8329.

 

MOTION:

Approve staff recommendation