FROM:
Engineering
SUBJECT:
Title
Approve a Memorandum of Understanding (MOU) with Cucamonga Valley Water District (CVWD) for the Construction of Domestic and Recycled Water Lines along Cherry Avenue and Victoria Avenue for the Building a Better Connected Inland Empire Project (Westgate at Cherry and Victoria Avenues)
End
RECOMMENDATION:
Recommendation
1. Approve and authorize the City Manager to enter into a Memorandum of Understanding (MOU) with Cucamonga Valley Water District (CVWD) for the Construction of Domestic and Recycled Water Lines along Cherry Avenue and Victoria Avenue for the Building a Better Connected Inland Empire Project (Westgate at Cherry and Victoria Avenues).
2. Authorize the payment to CVWD in the amount of $233,523.92 for water line improvements for the Building a Better Connected Inland Empire Project (Westgate at Cherry and Victoria Avenues).
3. Authorize the City Manager to enter into any future amendments to the MOU for a total not-to-exceed amount of $50,000.00.
End
COUNCIL GOALS:
• To invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.
• To invest in the City’s infrastructure (streets, sewers, parks, etc.) by providing for the development of new infrastructure.
DISCUSSION:
The Building a Better Connected Inland Empire Project is a federally funded project along Cherry Avenue from Baseline Avenue to just north of the SR 210 freeway and along Victoria Avenue from Cherry Avenue to Kestral Avenue within the Westgate Specific Plan Area. The project was successful with the award of a $15 Million FY 2022 Rebuilding American Infrastructure with Sustainability and Equity (RAISE) Grant.
Major street improvement will be completed with the Project including additional lane capacity, integrated traffic system, medians with protected left turns, street lights, signage, roundabout, raised landscape medians, approximately 5 miles of Class II bike trails, approximately 2.5 miles of Class I bike lanes, approximately 5 miles of ADA compliant sidewalks, approximately 0.5 miles of multi-use trails, pedestrian crosswalks, and countdown signal heads.
Utility infrastructure improvements are also incorporated into the project including the construction of 4,506 linear feet of 8-inch recycled water mains, 7,579 linear feet of 12-inch and 125 linear feet of 8-inch domestic water mains that will be owned and operated by the Cucamonga Valley Water District (CVWD).
The purpose of this MOU is to establish the terms, conditions, and mutual understanding between the City and CVWD regarding the construction of the Victoria Street Recycled Water Pipeline and Domestic Water Pipeline on Victoria Street and Cherry Avenue with the transfer of ownership and all associated rights, responsibilities, and liabilities.
The City, as part of the construction of the project improvements, will install the water lines and transfer ownership and maintenance responsibilities to CVWD upon completion and acceptance. As part of the construction of the water lines, fees for the plan check, inspection, and meter installation that will service the landscape and future development of the Westgate Specific Plan area are calculated in the amount of $134,816.28 for the recycled water line improvements and $98,707.64 for the domestic water line improvements, for a total amount of $233,523.92.
FISCAL IMPACT:
The fiscal impact associated with the approval of this item is $233,523.92 and is included in the current FY 2026-2027 Budget in the Westgate Cherry Avenue and Victoria Avenue Project No. 37600042-604-D-8335.
MOTION:
Approve staff recommendation.