File #: 25-0675    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 11/18/2025 In control: City Council Meeting
On agenda: 12/9/2025 Final action:
Title: Final Acceptance of Purchase and Installation of Metal Picnic Shelters at North Tamarind Park Project (SB-122-PW-23).
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

FROM:

Public Works

 

SUBJECT:

Title

Final Acceptance of Purchase and Installation of Metal Picnic Shelters at North Tamarind Park Project (SB-122-PW-23).

End

 

RECOMMENDATION:

Recommendation

1.                     Accept as complete the work performed by Western State Builders, Inc. for the Purchase and Installation of Metal Picnic Shelters at North Tamarind Park Project (SB-122-PW-23).

 

2.                     Authorize the City Manager to approve the additional contract authorization increase amount of $14,738.56.

 

End

 

COUNCIL GOALS:

                     Invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.

                     Invest in the City’s infrastructure (streets, sewers, parks, etc.) by providing for the development of new infrastructure.

 

DISCUSSION:

On June 13, 2023, the City Council awarded a construction contract to Western State Builders Inc. in the amount of $249,229.00 for the purchase and installation of three (3) Metal Picnic Shelters and authorized a 10% contingency amount of $24,923.00 for a total contract authorization of $274,152.00.

 

There were four contract change orders on this project:

                     Change Order No. 1 provided a credit of $84,884.00 and removed the planned picnic shelter at Miller Park due to concerns about increased loitering. The contract was adjusted to $164,345.00.

                     Change Order No. 2, approved by the City Council on September 9, 2025, added demolition of the existing shelter at North Tamarind Park and additional concrete work necessary for ADA-compliant sidewalks. The change order totaled $147,153.37, bringing the contract authorization total to $311,498.37.

                     Change Order No. 3 added $23,557.72 for extra concrete required for shelter footings after poor soil conditions were uncovered during excavation, increasing the contract to $335,056.09.

                     Change Order No. 4 issued a credit of $8,819.16 by removing irrigation repair and turf restoration items, which were completed by the City’s landscape contractor. The final adjusted contract amount was $326,236.93.

Western State Builders, Inc. finished the project on November 14, 2025, and all work has been accepted by the City for a final contract total of $326,236.93.

 

The final retention payment will be released thirty-five (35) days after the filing of the Notice of Completion with the County Recorder’s Office.

 

FISCAL IMPACT:

There is no fiscal impact associated with the approval of this item. The final contract cost for this project was $326,236.93. The funding was budgeted in the FY 2022/2023 CIP and Operating Budgets in project strings #38200005-302-F-8313, #38200005-302-O-8313, and #38200005-302-P-8313.

 

MOTION:

Approve Staff Recommendation