Title: Approve Amendment to Task Order for STC Traffic, Inc. for the Baseline Ave. and Palmetto Ave. Traffic Signal Project Design Services
Attachments: 1. Attachment No. 1- STC Traffic, Inc. - Amendment No. 3, 2. Attachment No. 2- Vicinity Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

FROM:

Engineering

 

SUBJECT:

Title

Approve Amendment to Task Order for STC Traffic, Inc. for the Baseline Ave. and Palmetto Ave. Traffic Signal Project Design Services

End

 

RECOMMENDATION:

Recommendation

1.                     Approve and authorize the City Manager to execute Amendment No. 3 to Task Order No. 4, for STC Traffic, Inc., in the amount of $8,010.00 for an amended task order total of $108,175.00 for additional plan revisions and design support services.

 

2.                     Approve and authorize the City Manager to execute any future amendments to the Task Order in the amount not to exceed $10,000.

 

End

 

COUNCIL GOALS:

                     To invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.

                     To invest in the City’s infrastructure (streets, sewers, parks, etc.) by providing for the development of new infrastructure.

                     To invest in the City’s infrastructure (streets, sewers, parks, etc.) by focusing on relief of traffic congestion.

 

DISCUSSION:

On June 22, 2022, the City of Fontana released a request for proposals (RFP) for the Baseline Ave. and Palmetto Ave. Traffic Signal Project Design Services to firms on the City’s Pre-qualified Engineering List (SQ-87-DE-19). On July 14, 2022, proposals were received and the City executed Task Order No. 4 with STC Traffic, Inc. in the amount of $75,365.00. On June 8, 2023, the City executed Task Order No. 4.1, Amendment No. 1 for additional design services to widen Baseline Avenue at the intersection, in the amount of $19,560.00, for a total contract amount of $94,925.00. On July 31, 2024, the City executed Task Order No. 4.2, Amendment No. 2 for additional potholing services in the amount of $5,240.00, for a total contract amount of $100,165.00.

 

Additional plan check comments require Amendment No. 3 to the existing task order in the amount of $8,010.00, for a total contract amount of $108,175.00. This amendment will cover STC Traffic, Inc.’s revisions to the plan to address all comments and complete the plans before bidding the project.

 

FISCAL IMPACT:

The fiscal impact associated with the approval of this item is $8,010.00 and is included in the 2025-26 budget in Baseline Ave. and Palmetto Ave. Traffic Signal Project (#37600031).

 

MOTION:

Approve staff recommendation.