Title: Final Acceptance of the Construction of the Public Works Concrete Maintenance Project (PW-24-133-SB)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

FROM:

Public Works

 

SUBJECT:

Title

Final Acceptance of the Construction of the Public Works Concrete Maintenance Project (PW-24-133-SB)

 

End

RECOMMENDATION:

Recommendation

Accept as complete the work performed by MAJ Engineering for the Public Works Concrete Maintenance Project (PW-24-133-SB) and approve the final construction amount of $210,527.00

End

 

COUNCIL GOALS:

                     Invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.

 

DISCUSSION:

On September 24, 2024, the City Council awarded a construction contract to MAJ Engineering for the Public Works Concrete Maintenance Project (PW-24-133-SB) in the amount of $210,527.00. MAJ Engineering completed the construction of the project on April 1, 2025. All work has been completed to the satisfaction of the City for the final amount of $210,527.00. This project was necessary to maintain a network of existing sidewalks, pedestrian access ramps, curbs, gutters, driveway approaches, and other miscellaneous concrete improvements.

 

The retention money will be released to the contractor thirty-five (35) days after the filing of the Notice of Completion with the County Recorder’s Office if no claims are filed with the City within this period.

 

FISCAL IMPACT:

Funds were budgeted in FY 2024/25 in the Capital Reinvestment Fund 601 in the Sidewalk Rehabilitation Project No. 37104326-601-A-8329, $102,527.00 and in Concrete Maintenance Operating Budgets 10137106-8130, $25,000.00, and 28137106- 8130, $83,000.00.

 

MOTION: