FROM:
Engineering
SUBJECT:
Title
Final Acceptance of Street, Storm Drain, Sewer, Landscape, and Signing & Striping Improvements on the northeast corner of Summit Avenue and Citrus Avenue for Tract No. 18825-1
End
RECOMMENDATION:
Recommendation
1. Accept as complete the street, storm drain, sewer, landscape, and signing & striping improvements for Tract No. 18825-1, located on the northeast corner of Summit Avenue and Citrus Avenue.
2. Adopt Resolution No. 2024-115, accepting sewers in Tract No. 18825-1 as part of the City sewer system.
End
COUNCIL GOALS:
• To invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.
• To invest in the City’s infrastructure (streets, sewers, parks, etc.) by providing for the development of new infrastructure.
DISCUSSION:
KB Homes, Inc., constructed street, streetlight, storm drain, sewer, landscape, and signing & striping Improvements for Tract No. 18825-1, located on the northeast corner of Summit Avenue and Citrus Avenue. Tract No. 18825-1 is a single-family subdivision and has a total of 77 lots.
The street, storm drain, sewer, landscape, and signing & striping improvements for Tract No. 18825-1 are complete and acceptance by the City Council is required pursuant to Fontana Municipal Code Section 26-184(b). The streetlight improvements are installed by Southern California Edison (SCE) and will be an SCE facility, therefore, acceptance by the City Council is not required.
The street, storm drain, sewer, landscape, and signing & striping improvements have been completed to the satisfaction of the Department of Engineering. By accepting the improvements as complete, the City will be taking over the maintenance of these improvements. SCE will be taking over the maintenance of the streetlight improvements.
This action will also authorize the release of the Faithful Performance Bond, which was posted to guarantee performance of the Subdivision Agreement. It will also authorize the release of the Labor and Material Bond after six (6) months and the Warranty Bond after twelve (12) months, less the total of any claims received by this date. The street, streetlight, storm drain, sewer and signing & striping improvements have met all Conditions of Approval and the improvements were inspected by the Department of Engineering.

FISCAL IMPACT:
Appropriate funding for the maintenance work is included in the FY 2024-25 budget under the Public Works & Engineering Department, Utilities and Streets Division and Park and Landscape Division.
MOTION:
Approve staff recommendation.