Legislation Details

File #: 26-1182    Version: 1 Name:
Type: Consent Calendar Status: Agenda Ready
File created: 7/27/2026 In control: City Council Meeting
On agenda: 9/8/2026 Final action:
Title: Final Acceptance for the Jessie Turner Center Indoor Basketball Court Replacement Project (PW-26-105-SB)
Attachments: 1. Attachment No. 1- Gym Floor Notice of Completion.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

FROM:

Public Works

 

SUBJECT:

Title

Final Acceptance for the Jessie Turner Center Indoor Basketball Court Replacement Project (PW-26-105-SB)

 

End

RECOMMENDATION:

Recommendation

Accept as completed work performed by McWil Sports Surfaces Inc. for the installation of a new gym floor, contract PW-26-105-SB, located at 15556 Summit Avenue, Jessie Turner Community Center.

 

End

COUNCIL GOALS:

                     Invest in the City’s infrastructure (streets, sewers, parks, etc.) by maintaining and improving the city's existing infrastructure.

 

DISCUSSION:

On April 16, 2026, the City Council awarded a construction contract to McWil Sports Surfaces Inc. for the Jessie Turner basketball court floor replacement project in the amount of $355,395.00.

 

MCWil Sports Surfaces Inc. completed the project to the City’s satisfaction; all work was accepted by the City on June 10, 2026, for the contract amount of $355,395.00. The notice was filed with San Bernardino County Records on July 16, 2026, DOC 2026-0183299.

 

FISCAL IMPACT:

There is no fiscal impact associated with the approval of this item.

 

MOTION:

Approve staff recommendation